Dubai Municipality Plans 34 Parks and Full Drainage Coverage in Al Awir by 2032

Dubai Municipality's plans for 34 Al Awir parks and full sewage and stormwater drainage coverage for 10,297 residential plots set out a phased programme of works running to 2032.

By

Editor-in-Chief

Published 4 min read

Dubai Municipality Plans 34 Parks and Full Drainage Coverage in Al Awir by 2032

Dubai Municipality has unveiled plans to develop 34 parks in Al Awir and expand sewage and rainwater drainage networks to serve 10,297 residential plots, under infrastructure projects scheduled for completion in phases through 2032. The plans for the Al Awir parks and networks cover Al Awir 1 and Al Awir 2, with the aim of providing full sewage and stormwater drainage coverage across 67.01 square kilometres.

The programme also includes automated irrigation systems, landscaping improvements and upgrades to public facilities in residential areas. The municipality outlined the projects during a meeting with residents at Al Khawaneej and Al Awir Council, where officials discussed development priorities and gathered feedback on local services and infrastructure.

For background on other infrastructure work in the emirate, see our report: Sheikh Hamdan Reviews Dubai Metro Blue Line as Construction Reaches 29 Per Cent.

34 Al Awir parks to open between 2029 and 2032

The Al Awir parks programme comprises 34 parks across the two districts. They include Greater Al Awir Park, which is currently being designed and is scheduled to open in the first quarter of 2029.

The remaining 33 parks will be developed in four phases between 2027 and 2030, with openings scheduled through 2032. Under the first phase, one park is planned for development in 2027 and is expected to open in the first quarter of 2029.

Another 13 parks will be developed under the 2028 programme, with openings scheduled for early 2030. A further 13 parks are planned for development in 2029 and are expected to open in the first quarter of 2031, while the final six parks will be developed in 2030 and are scheduled to open in early 2032.

Park development timeline

Parks Number Development Scheduled opening
Greater Al Awir Park 1 Currently being designed First quarter of 2029
2027 programme 1 2027 First quarter of 2029
2028 programme 13 2028 Early 2030
2029 programme 13 2029 First quarter of 2031
2030 programme 6 2030 Early 2032
Total 34 2027 to 2030 Through 2032

Read more: our report on Dubai Run 2026 Closes Four Roads Including Sheikh Zayed Road From 3am to 10am on 22 November.

Sewage and stormwater drainage coverage

The municipality also announced three sewage and rainwater drainage projects aimed at achieving 100 per cent coverage in Al Awir 1 and Al Awir 2.

In Al Awir 1, two projects will expand existing networks, which currently cover 53.4 per cent of the area and serve 5,072 residential plots. The projects aim to extend coverage to 9,490 plots across 39.87 square kilometres by 2030.

In Al Awir 2, a separate project will provide sewage and rainwater drainage services to 807 residential plots across 27.14 square kilometres, with completion planned for 2032. The projects are intended to support residential development and improve infrastructure capacity in both districts.

District Projects Current network Plots to be served Area Completion
Al Awir 1 2 53.4 per cent of the area, 5,072 plots 9,490 39.87 sq km 2030
Al Awir 2 1 — 807 27.14 sq km 2032
Total 3 — 10,297 67.01 sq km Through 2032

For related coverage, see our report: UAE Weather Forecast: Rain Possible in Eastern and Northern Areas as NCM Warns of Overnight Fog.

Irrigation and landscaping projects

Three additional irrigation and landscaping projects are planned for residential areas and internal roads in Al Awir and Wadi Al Amardi. Two of them, being developed in coordination with the Mohammed bin Rashid Housing Establishment, will serve Emirati housing developments in Al Awir and Wadi Al Amardi, with implementation scheduled for 2027.

A third project will introduce automated irrigation systems and landscaping along internal roads in Al Awir 1 and Al Awir 2 in 2029.

Works on Al Awir Street

The municipality also reviewed ongoing landscaping improvements along Al Awir Street and Sheikh Zayed bin Hamdan Street. Work on the Al Awir Street project began in June 2026 and covers approximately six kilometres, including the intersection with Sheikh Mohammed bin Zayed Street. The improvements include irrigation networks, landscaping and a pumping station.

Another project covers sections of Al Awir Street and Sheikh Zayed bin Hamdan Street, including the cycling track adjacent to Mushrif Park.

Support for Emirati homeowners

During the meeting, the municipality highlighted initiatives aimed at helping Emiratis planning to build their homes. These include 18 residential villa designs available through the Build in Dubai platform, with layouts ranging from single-storey homes to three-storey properties and built-up areas of between 322 and 975 square metres.

The municipality also presented a programme to train 500 Emiratis over five years in residential project management, enabling eligible participants to obtain licences to supervise housing construction projects.

Read more: our report on Dubai Court Cancels 25-Year Land Investment Deal in Umm Ramool and Orders Dh700,000 Payment.

Smart services and public health

Other initiatives presented at the meeting included smart feeding stations for stray cats that operate in conjunction with plastic bottle recycling. The municipality also set out plans for a veterinary services complex incorporating artificial intelligence, animal shelters, clinics and specialised facilities.

It highlighted its Safe Water for a Healthy Community initiative, which provides water tank inspections and disinfection services for senior citizens and people of determination. The initiative, implemented in coordination with the Community Development Authority, has so far covered 92 homes across Dubai.

For background, see our coverage of Mohammed bin Rashid Al Maktoum Global Water Award Draws Applications From 83 Countries in Fifth Cycle, and our report on UAE Launches mira AI Assistant for Government Services, With Rollout From March 2027. Information on government services is available on the UAE Government portal, and official announcements are carried by the Emirates News Agency.

Frequently Asked Questions

How many parks are planned in Al Awir?

Dubai Municipality plans 34 parks across Al Awir 1 and Al Awir 2, including Greater Al Awir Park, which is scheduled to open in the first quarter of 2029.

When will the last Al Awir parks open?

The final six parks will be developed in 2030 and are scheduled to open in early 2032.

How many residential plots will the drainage projects serve?

The three sewage and rainwater drainage projects will serve 10,297 residential plots across 67.01 square kilometres: 9,490 plots in Al Awir 1 by 2030 and 807 plots in Al Awir 2 by 2032.